The construction project at York High School continues to move full steam ahead. Since school dismissed on May 17th, crews have been working many hours.
FINE ARTS ADDITION
• Drywall work has been finished
• Painting has begun
• Cabinetry is being installed
GYM ADDITION
• Concrete gym floor has been poured
• Electrical and mechanical rough-ins continue
• Gym will most likely not be done by August 20th when school resumes but should be done in September
DISTRICT STORAGE/ADMIN BUILDING
• The final “punch list” is being conducted by June 12th with occupancy to most likely take place by July 8th
INTERIOR REMODEL
• Demolition work is in full swing and is scheduled to be done by June 18th
• HVAC, Electrical, Plumbing, and Fire Sprinkler work is ongoing
• Skylights will begin to be installed this month
MISCELLANEOUS
• The additional south parking lot that will add 46 parking stalls will begin to take shape in the next few weeks
• It is still our goal to regain full occupancy by August 5th since school resumes on August 20th
• The project is not scheduled for total completion until November 30, 2013.