Wednesday, June 12, 2013

YHS Construction Update

The construction project at York High School continues to move full steam ahead. Since school dismissed on May 17th, crews have been working many hours.

FINE ARTS ADDITION
• Drywall work has been finished
• Painting has begun
• Cabinetry is being installed

GYM ADDITION
• Concrete gym floor has been poured
• Electrical and mechanical rough-ins continue
• Gym will most likely not be done by August 20th when school resumes but should be done in September

DISTRICT STORAGE/ADMIN BUILDING
• The final “punch list” is being conducted by June 12th with occupancy to most likely take place by July 8th

INTERIOR REMODEL
• Demolition work is in full swing and is scheduled to be done by June 18th
• HVAC, Electrical, Plumbing, and Fire Sprinkler work is ongoing
• Skylights will begin to be installed this month

MISCELLANEOUS
• The additional south parking lot that will add 46 parking stalls will begin to take shape in the next few weeks
• It is still our goal to regain full occupancy by August 5th since school resumes on August 20th
• The project is not scheduled for total completion until November 30, 2013.